Las Piñas station is an under construction on the Manila Light Rail Transit System Line 1. It is part of the Line 1 South Extension Project. It is one of two proposed Line 1 stations in Las Piñas, the other being Manuyo Uno station.

Las Piñas
Manila Light Rail Transit System
LocationPulang Lupa Uno, Las Piñas
Owned byLight Rail Transit Authority
Line(s)Line 1

The Line 1 plan calls for a mostly elevated extension of approximately 11.7 km. The extension will have 8 passenger stations with an option for 2 future stations (Manuyo Uno and Talaba). [1]

As of December 31, 2020, the project is 50.61% complete. Partial operation of the project will be in the end of 2021 and full operation will be in first quarter of 2024.